Home · AI

AI in project management

AI does not replace the project manager; the project manager who uses it sees risk sooner.

Many people talk about “AI in project management”. I prefer to show it: where it genuinely helps, a real case, a sample output, the method I work with, and the places I deliberately stay away from.

Capability

AI in oil and gas project management — exactly where it helps

The value of this capability does not come from the tool. The tool is available to everyone. What is rare is knowing, on an oil and gas EPC project, which question is worth asking, what the right output looks like, and which part of the schedule a wrong answer burns. That judgement comes from twenty years in the field, not from the tool.

Why this combination is rare

Most people who know AI well have never defended a real critical path in front of a client; and most people who know EPC projects have never tried these tools in daily work. My work sits on that overlap: I place the tool at a specific point in the project’s reporting and decision cycle, with a defined output and one person accountable for each output.

Seven specific places in the project cycle

Each has a defined input and a defined output. None is a “general analysis”.

Schedule and critical path

Comparing a schedule update with the baseline and extracting the activities that actually drove the critical path change — not a long list of lagging activities.

OutputA short list of delay drivers, with estimated effect on the completion date and the responsible discipline.

Risk capture from minutes and correspondence

Processing weekly meeting outputs and contractor correspondence with a fixed template, so a risk enters the register before it reaches the critical path.

OutputProposed risk register entries — event, likely impact, responsible discipline — for the planner’s approval.

Progress reporting and status narrative

Turning progress data, S-curves and SPI and CPI into a status narrative written the same way every week and comparable over time.

OutputDraft weekly and monthly reports in consistent language with figures traceable to source.

Delay analysis, claims and extension of time

Building a chain of evidence from masses of correspondence: event, date, relevant contract clause and claimed schedule impact.

OutputA chronologically ordered evidence table as input for the claims specialist — not as the claim itself.

Engineering document consistency

Checking inconsistencies between P&IDs, datasheets, line lists and specifications before a document reaches IFC and change gets expensive.

OutputA list of candidate inconsistencies for the discipline engineer to judge.

Procurement and long-lead items

Tracking vendor document status and delivery schedules of critical items against installation need, with early warning on items losing their float.

OutputA warning list of critical items, ordered by distance to need date.

Enabling the project office team

Writing standard prompt templates and usage guidelines so output is repeatable across the team and not dependent on individual taste.

OutputA ready template pack, with a short introductory and practice workshop.

A real case

A contract at the end of its term, and nobody knew whose fault the delay was

The situation

An engineering services contract had reached the end of its term, a significant part of the work was still open, and the two parties disagreed about who was responsible for the delay. The file held the contract and its general conditions plus dozens of letters, minutes and attachments — several hundred pages nobody had time to read in full. A decision had to be made and there was no basis for making it.

The usual approach, and why it didn’t work

Normally one or two people read the file piece by piece and each understands part of the story. The problem is not carelessness; the key events are spread across months and hundreds of pages, and putting them side by side is beyond anyone’s memory. What gets lost is rarely a document — it is the relationship between two documents.

What we did

  • The whole file was read with one fixed template: contract, general conditions, correspondence and minutes — all against a single question, not free interpretation.
  • Three things came out of it: a timeline of key events, a map of which side of the table each stoppage belonged to, and the list of contract clauses relevant to each event.
  • The timeline showed something no monthly report had highlighted: a long wait for a decision that was the client’s to make, without which part of the work was technically impossible to start.
  • Seeing that changed the frame of the whole problem. It was not a “consultant delay”; it was a missing prerequisite the other party was obliged to provide — and in the contract those are two entirely different clauses.

What was delivered

A decision memo for management and a draft letter to the client with specific requests, each item referenced to a clause of the same contract. Work that would have taken weeks of reading and cross-referencing produced something decidable within days.

The boundary that didn’t move

No document from this file went into a public AI service. The analysis output was a recommendation, not a decision: every item was read and approved before it went anywhere, and responsibility stayed with its signatory. The tool raised the speed of seeing; it did not move the responsibility for the decision.

Before and after AI

The path of a warning, from data to action

The difference is not how fast a report is typed; it is the gap between an event and its arrival on the decision-maker’s desk.

Typical process

  1. Progress report
  2. Excel
  3. Manual review
  4. Management meeting

Warnings usually surface in the monthly meeting — weeks after the first signal.

AI-assisted

  1. Project data
  2. AI analysis
  3. Risk & delay detection
  4. Specialist approval
  5. Management action

The tool surfaces the signal sooner; a specialist approves it and the manager decides.

Sample output

Project risk analyser — a sample output

Demonstration with fictional data. No figure or name in this section comes from a real project.

Fictional project: gas processing unit, construction stage, month-8 report

Inputs

Risk register
42 open risks; last updated three weeks ago
Schedule
Monthly update against the approved baseline
Progress report
Contractor’s monthly report and weekly minutes

Management dashboard

0.87SPI
0.94CPI
−18 daysCritical path float
7Open risks without owner

Emerging risks — top five

RiskSignal in the dataLikely impactTrend
Late delivery of gas compressorsVendor documents returned twice; shipping date moved in week-32 minutesAbout six weeks on installation and pre-commissioningRising
Shortage of qualified weldersInch-dia productivity below plan three weeks runningUnit 2 piping front falling behindRising
P&ID change after IFCFour open change requests on one systemRework in instrumentation procurementNew
Slow work permits in live areaAverage permit time up from one day to threeTie-in fronts slowing downRising
Gap between reported and measured progressSix-percent difference between contractor report and installed quantitiesDecisions based on an optimistic pictureStable

Schedule threats

  • The critical path runs through compressor installation; without action, pre-commissioning slips about six weeks.
  • Two Unit 2 piping activities with less than five days of float are close to the critical path.
  • Tie-in fronts are bunched into one shutdown window of the adjacent unit.

Risks missing from the register

  • Tie-in dates depend on the adjacent unit’s shutdown plan — mentioned in three sets of minutes, not in the register.
  • Warehouse capacity for sensitive equipment in the hot season — mentioned in the contractor’s report.
  • Change of instrument cable supplier — mentioned in correspondence, schedule impact not assessed.

Recommended actions — for the project manager’s decision

ActionProposed ownerDue
Expediting meeting with the compressor vendor and fix the shipping dateProcurement managerWeek 34
Re-sequence Unit 2 piping and add one spreadConstruction managerWeek 35
Hold procurement of affected items until the P&ID change closesEngineering managerWeek 33
Review the progress measurement method with the contractorProject controlsWeek 34

The boundary that doesn’t move

Tool output is a recommendation, not a decision: every item is traced back to its source in the data and approved by the planner before it reaches the management meeting. Real project data is processed only inside the client’s approved environment or in anonymised form.

See this output on your own project

From the problem, not the tool

How an engagement works

Every engagement follows these five steps; we start from the problem, not the tool.

  1. Choosing a real, small problem from the project’s current cycle: one report, one register, one recurring check. Not a transformation programme.
  2. Defining the exact shape of the output and the person responsible for approving it — before any technical work.
  3. Deciding on data: which data is anonymised, which stays only in the client’s approved environment, and which never enters the tool.
  4. Building a fixed template and running it in parallel for two to three reporting periods, alongside the current method, not instead of it.
  5. Measuring two numbers — preparation time, and the lag between an event and its capture — then deciding to continue or stop.

A boundary that doesn’t move

The tool raises the speed of seeing; it doesn’t move the responsibility for the decision.

No document, drawing, schedule or project data goes into a public AI service.

Five written commitments

What I do and don’t do with your project data

A promise of “I won’t publish it” is not enough. In most oil and gas contracts, simply putting data into an external service is a breach of confidentiality, even if it is never published. That is why I have written these five commitments down.

  1. I never put your documents, drawings, schedules or project data into a public AI service.
  2. I use AI on project data only inside an environment the client has approved, or on anonymised data.
  3. Anonymisation means removing the client’s name, contract number, document identifiers, coordinates and anything that makes the project identifiable.
  4. Tool output is reviewed and approved by the accountable person before it enters any official document.
  5. I state this position in the proposal and in the first technical meeting — before anyone asks.

Why this clause sells, not just protects

When an oil and gas client hears that someone uses AI, the first reaction is concern. A manager who says “your data does not go into any external service” before being asked turns that concern into trust. This clause is the one place where confidentiality becomes a competitive advantage.

Clear boundaries

What is not done

This list is as much a part of my work as the one above. A boundary not stated at the start is broken sooner or later.

  • AI does not make project decisions. The decision belongs to the project manager, and so does the signature.
  • Tool output does not go directly into any official document, minutes or contractual correspondence.
  • The planner or discipline engineer is not replaced; their repetitive work shrinks so their time goes to judgement.
  • No figure whose source cannot be traced enters a report.
  • No work is done on confidential data outside the client’s approved environment — the full clause is on this page.

AI credentials

Training background

Four certificates: three course certificates from the Project Management Institute (PMI) — the issuer of the PMP — and one “AI Consultant” certificate from CPD, Canada. The exact status of each is shown beside it.

  • Generative AI Overview for Project ManagersProject Management Institute (PMI) — Certificate of completion — issued 8 July 2026 · Certificate image
  • Practical Application of Generative AI for Project ManagersProject Management Institute (PMI) — Certificate of completion — issued 10 July 2026 · Certificate image
  • Talking to AI: Prompt Engineering for Project ManagersProject Management Institute (PMI) — Certificate of completion — issued 1 August 2026 · Certificate image
  • Certified AI ConsultantCareerpreneur AcademyCertified by CPD (Continuing Professional Development), Canada — 120 CPD points — issued 2 October 2026, ID CAPC-2026-0MJSD0 · Certificate image

The sentence this page closes with

AI does not replace the project manager; the project manager who uses it sees risk sooner. All the value of this line of work is in that word: “sooner”.

Ready text

Ready-to-use sentence for proposals

In this engagement, no project document or data is entered into a public AI service. These tools are used only on anonymised data or within the client’s approved environment, and responsibility for every output rests with the project team before it enters official documents.

If you want to know exactly where AI helps in managing your project

One 60-minute diagnostic session is enough to find the right first cycle together.

Explore AI for Your Project